Doffin – tenders and notices
| Notice | Type | Published | Est. value (NOK) |
|---|---|---|---|
| Revised_Installation of a CO2 Quality Monitoring system - FEED + EPC | Tender · Expired | 2024-07-14 | NOK 30.0m |
| CO2 QUALITY MONITORING AT NORTHERN LIGHTS FACILITIES AT ØYGARDEN, NORWAY | Award | 2024-07-09 | NOK 10.0m |
| Installation of a CO2 Quality Monitoring system - FEED + EPC | Tender · Expired | 2024-06-01 | NOK 30.0m |
| Co2 filter for CO2 storage plant | Tender · Expired | 2024-04-05 | NOK 14.0m |
| CO2 QUALITY MONITORING AT NORTHERN LIGHTS FACILITIES AT ØYGARDEN, NORWAY | Tender · Awarded | 2024-03-23 | NOK 10.0m |
| Commissioning of CO2 plant | Tender · Expired | 2023-12-14 | NOK 15.0m |
| Civil arbeider Kårstø prosessanlegg, Sture terminal og Kollsnes prosessanlegg | Award | 2023-04-11 | |
| Civil arbeider Kårstø prosessanlegg, Sture terminal og Kollsnes prosessanlegg | Tender | 2022-03-25 | |
| Boligleir Kårstø | Tender | 2022-02-22 |